2026 STREET CONSTRUCTION UPDATES

  WEEK OF
NOVEMBER 2- NOVEMBER 6
WEEK OF
NOVEMBER 9 -NOVEMBER 13

  Sterling Avenue

Greenfield Street

The project is complete.

 
Elm Street
(Division – Cecil)
The Contractor is scheduled to pave the roadway and finish any punch list items remaining. The Contractor is scheduled to finish paving the roadway and remove traffic control.
Reed Street (Washington to Cecil) The Contractor is scheduled to pave the roadway and finish any punch list items remaining. The Contractor is scheduled to finish paving the roadway and remove traffic control.
Henry Street (Douglas to Monroe) The Contractor is scheduled to pave the roadway and finish any punch list items remaining. The Contractor is scheduled to finish paving the roadway and remove traffic control.

Notes: 1)  This schedule could vary depending on site conditions and weather.

2)   Please contact the Department of Public Works at 920-886-6240 if you have any questions or concerns during the construction project, especially related to safety.

3)   Our inspector and/or the contractor will be contacting customers prior to connecting the new water services, which will require a water service interruption. We will work to make the connection during a time that is convenient for the customers and the contractor.

4)   Please return the Property Owner Authorization Form to the Department of Public Works as soon as possible.The co