2023 STREET CONSTRUCTION UPDATES
WEEK OF JUNE – JUNE 9 |
WEEK OF JUNE 12 – JUNE 16 |
|
Burr Ave.
Chestnut St. (Division – Oak) Chestnut Ct. Dieckhoff St. (Oak – Chestnut) Laudan Blvd. (Oak – Elm) |
The contractor is scheduled to continue private sewer and water service construction and begin storm sewer construction.
All Streets will be closed to through traffic during construction, until October/November. |
The contractor is scheduled to continue private sewer and water service construction and begin storm sewer construction. |
Columbian Ave.
(Elm – Congress)
|
The contractor is scheduled to finish private sewer and water service construction.During construction the roadway will be closed to through traffic. | Rest Period. A rest period is required by the contractor to allow the sewer trench backfill time to settle prior to street construction. |
Brantwood Dr./Ct. | The contractor is scheduled to begin water main construction. | Rest Period. A rest period is required by the contractor to allow the sewer trench backfill time to settle prior to street construction. |
Charles Ct. Hughes Ct. Memorial Ct. Patrick Ct. | The Contractor is scheduled to begin water main construction. | The Contractor is scheduled to continue water main construction. |
Notes: 1) This schedule could vary depending on site conditions and weather.
2) Please contact the Department of Public Works at 920-886-6240 if you have any questions or concerns during the construction project, especially related to safety.
3) Our inspector and/or the contractor will be contacting customers prior to connecting the new water services, which will require a water service interruption. We will work to make the connection during a time that is convenient for the customers and the contractor.
4) Please return the Property Owner Authorization Form to the Department of Public Works as soon as possible.