Construction Updates

 

2023 STREET CONSTRUCTION UPDATES

  WEEK OF
JUNE  – JUNE 9
WEEK OF
JUNE 12 – JUNE 16
Burr Ave.

Chestnut St.

(Division – Oak)

Chestnut Ct.

Dieckhoff St.

(Oak – Chestnut)

Laudan Blvd.

(Oak – Elm)

The contractor is scheduled to continue private sewer and water service construction and begin storm sewer construction.

All Streets will be closed to through traffic during construction, until October/November.

The contractor is scheduled to continue private sewer and water service construction and begin storm sewer construction.
Columbian Ave.

(Elm – Congress)

 

 

The contractor is scheduled to finish private sewer and water service construction.During construction the roadway will be closed to through traffic. Rest Period.  A rest period is required by the contractor to allow the sewer trench backfill time to settle prior to street construction.
 
Brantwood Dr./Ct. The contractor is scheduled to begin water main construction. Rest Period.  A rest period is required by the contractor to allow the sewer trench backfill time to settle prior to street construction.
Charles Ct.  Hughes Ct.  Memorial Ct.  Patrick Ct. The Contractor is scheduled to begin water main  construction. The Contractor is scheduled to continue water main  construction.

Notes: 1)  This schedule could vary depending on site conditions and weather.

2)   Please contact the Department of Public Works at 920-886-6240 if you have any questions or concerns during the construction project, especially related to safety.

3)   Our inspector and/or the contractor will be contacting customers prior to connecting the new water services, which will require a water service interruption. We will work to make the connection during a time that is convenient for the customers and the contractor.

4)   Please return the Property Owner Authorization Form to the Department of Public Works as soon as possible.